Which one of the following is NOT an input to the perfo…

There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process?

A.
Risk register

B.
Cost management plan

C.
Risk management plan

D.
Enterprise environmental factors