Which of the following would be the MOST serious risk where a systems development life cycle methodology is
inadequate?

PrepAway - Latest Free Exam Questions & Answers

A.
The project will be completed late.

B.
The project will exceed the cost estimates.

C.
The project will be incompatible with existing systems.

D.
The project will fail to meet business and user needs.

Explanation:
The systems development life cycle (SDLC), also referred to as the application development life-cycle, is a term
used in systems engineering, information systems and software engineering to describe a process for planning,
creating, testing, and deploying an information system. The systems development life-cycle concept applies to
a range of hardware and software configurations, as a system can be composed of hardware only, software
only, or a combination of both.
The most important stages of the systems development life cycle are the early requirement gathering and
design phases. If the system requirements are not correctly determined, the system will not meet the needs of
the business and users.
A: This question is asking for the MOST serious risk. A project completed late is inconvenient but a system that
fails to meet business and user needs is a more serious risk.
B: This question is asking for the MOST serious risk. A project that exceeds cost estimates is a pain but a
system that fails to meet business and user needs is a more serious risk.
C: This question is asking for the MOST serious risk. A project that is incompatible with existing systems is not
good but new systems could be deployed. However, a system that fails to meet business and user needs is no
good to anyone.