ISC Exam Questions

Which of the following would be the FIRST step to take when implementing a patch management program?

Which of the following would be the FIRST step to take when implementing a patch management
program?

A.
Perform automatic deployment of patches.

B.
Monitor for vulnerabilities and threats.

C.
Prioritize vulnerability remediation.

D.
Create a system inventory.