Which of the following statements pertaining to the maintenance of an IT contingency plan is incorrect?

PrepAway - Latest Free Exam Questions & Answers

A.
The plan should be reviewed at least once a year for accuracy and completeness.

B.
The Contingency Planning Coordinator should make sure that every employee gets an up-to-date copy of
the plan.

C.
Strict version control should be maintained.

D.
Copies of the plan should be provided to recovery personnel for storage offline at home and office.

Explanation:
The Contingency Planning Coordinator is not responsible to distribute the contingency plan to all employees.
Incorrect Answers:
A: Once a continuity plan is developed, it actually has to be put into action. The people who are assigned
specific tasks need to be taught and informed how to fulfill those tasks, and dry runs must be done to walk
people through different situations. The drills should take place at least once a year, and the entire program
should be continually updated and improved.
C: Version control is critical. A strict version control of the IT contingency should be kept.
D: There should be two or three copies of these plans. One copy may be at the primary location, but the other
copies should be at other locations in case the primary facility is destroyed.

Harris, Shon, All In One CISSP Exam Guide, 6th Edition, McGraw-Hill, 2013, p. 951