Which of the following rules pertaining to a Business Continuity Plan/Disaster Recovery Plan is incorrect?

PrepAway - Latest Free Exam Questions & Answers

A.
In order to facilitate recovery, a single plan should cover all locations.

B.
There should be requirements to form a committee to decide a course of action. These decisions should be
made ahead of time and incorporated into the plan.

C.
In its procedures and tasks, the plan should refer to functions, not specific individuals.

D.
Critical vendors should be contacted ahead of time to validate equipment can be obtained in a timely
manner.

Explanation:
A single plan is Always the best idea. Depending on the size of your organization and the number of people
involved in the DRP effort, it may be a good idea to maintain multiple types of Recovery Plans documents.Incorrect Answers:
B: A Business Continuity Plan committee needs to be put together. This committee decides course of actions
that are implemented in the Business Continuity Plan.
C: Business continuity planning is focused on keeping business functions uninterrupted when a disaster strikes.
D: The Business Continuity Plan risk assessment should include continuity risks due to outsourced vendors and
suppliers. Critical vendors should be contacted to ensure that necessary equipment can be obtained.

Stewart, James M., Ed Tittel, and Mike Chapple, CISSP: Certified Information Systems Security Professional
Study Guide, 5th Edition, Sybex, Indianapolis, 2011, p. 661