ISC Exam Questions

Which of the following is NOT a major element of Business Continuity Planning?

Which of the following is NOT a major element of Business Continuity Planning?

A.
Creation of a BCP committee

B.
Business Impact Assessment (BIA)

C.
Business Continuity Plan Development

D.
Scope plan initiation