ISC Exam Questions

Which of the following enables the person responsible f…

Which of the following enables the person responsible for contingency planning to focus risk management
efforts and resources in a prioritized manner only on the identified risks?

A.
Risk assessment

B.
Residual risks

C.
Security controls

D.
Business units

Explanation:
A risk assessment is a critical part of the disaster recovery planning process. In disaster recovery planning,
once you’ve completed a business impact analysis (BIA), the next step is to perform a risk assessment.
Once risks and vulnerabilities have been identified, i.e. after the risk assessment has been completed, four
types of defensive responses can be considered:
Protective measures
Mitigation measures
Recovery activities
Contingency plans
Incorrect Answers:
B: Contingency plans depend on risk assessments, not on residual risks. The residual risk is remaining risk
after the security controls have been applied.
C: Contingency plans depend on risk assessments, not on Security controls.
D: Contingency plans depend on risk assessments, not on Business units.

http://searchdisasterrecovery.techtarget.com/Risk-assessments-in-disaster-recovery-planning-A-free-IT-riskassessment-template-and-guide