Which of the following alternative business recovery strategies would be LEAST appropriate in a larg

Which of the following alternative business recovery strategies would be LEAST appropriate in a
large database and on-line communications network environment where the critical business
continuity period is 7 days?

A.
Hot site

B.
Warm site

C.
Duplicate information processing facilities

D.
Reciprocal agreement