PrepAway - Latest Free Exam Questions & Answers

What would you call a strategy where the alternate site…

Recovery Site Strategies for the technology environment depend on how much downtime an organization can
tolerate before the recovery must be completed. What would you call a strategy where the alternate site is
internal, standby ready, with all the technology and equipment necessary to run the applications?

PrepAway - Latest Free Exam Questions & Answers

A.
External Hot site

B.
Warm Site

C.
Internal Hot Site

D.
Dual Data Center

Explanation:
An internal hot site is standby ready with all the technology and equipment necessary to run the applications to
be recovered there.
Incorrect Answers:
A: An external hot site has equipment on the floor waiting for recovery, but the environment must be rebuilt for
the recovery. An external hot site is not standby ready.
B: A warm site is not standby ready. A warm site is a leased or rented facility that is usually partially configured
with some equipment, such as HVAC, and foundational infrastructure components, but not the actual
computers. In other words, a warm site is usually a hot site without the expensive equipment such as
communication equipment and servers.
D: A dual data center is employed for application that canAccept any downtime without unacceptably impacting
the business. A dual data center would be more than standby ready, but it would be more expensive.