After a company is out of an emergency state, what should be moved back to the original site first?

PrepAway - Latest Free Exam Questions & Answers

A.
Executives

B.
Least critical components

C.
IT support staff

D.
Most critical components

Explanation:
The salvage team must ensure the reliability of primary site. This is done by returning the least-mission-critical
processes to the restored original site to stress – test the rebuilt network. As the restored site shows resiliency,
more important processes are transferred.
Incorrect Answers:
A: There is no priority to move the Executives back to the original site fast. The salvage team, not the
Executives brings the original site back in order.
C: The salvage team, not the IT support staff brings the original site back in order. There is no priority to move
the IT support staff back to the original site fast.
D: The most critical operations should be to the primary site after, before, the other less critical operations have
been moved.

Stewart, James M., Ed Tittel, and Mike Chapple, CISSP: Certified Information Systems Security Professional
Study Guide, 5th Edition, Sybex, Indianapolis, 2011, p. 669