what document are Tomas and the stakeholders working in this scenario?

Tomas is the project manager of the QWS Project and is worried that the project stakeholders will
want to change the project scope frequently. His fear is based on the many open issues in the
project and how the resolution of the issues may lead to additional project changes. On what
document are Tomas and the stakeholders working in this scenario?

Which of the following risk response planning techniques will you use to shift the impact of a threat to a thi

You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your
company. You have completed the risk analysis processes for the risk events. You and the project
team have created risk responses for most of the identified project risks. Which of the following risk
response planning techniques will you use to shift the impact of a threat to a third party, together
with the responses?