PrepAway - Latest Free Exam Questions & Answers

Category: CSSLP

Exam CSSLP: Certified Secure Software Lifecycle Professional

What component of the change control system would review the proposed changes’ impact on the features an

Henry is the project manager of the QBG Project for his company. This project has a budget of
$4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project,
has introduced a scope change request for additional deliverables as part of the project work.
What component of the change control system would review the proposed changes’ impact on the
features and functions of the project’s product?


Page 30 of 34« First...1020...2829303132...Last »