The temperature of 430 is called what?

Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project’s end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down.
The temperature of 430 is called what?

What should Walter also update in this scenario considering the risk event?

Walter is the project manager of a large construction project. He’ll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?

What approach can Amy take to create a bias against risks that will affect the schedule of the project?

Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?

What is the primary advantage to group risks by common causes during qualitative risk analysis?

Courtney is the project manager for her organization. She is working with the project team to complete the qualitative risk analysis for her project. During the analysis Courtney encourages the project team to begin the grouping of identified risks by common causes. What is the primary advantage to group risks by common causes during qualitative risk analysis?

What risk response is this?

You are the project manager of the YHG project for your company. Within the project, you and the project team have identified a risk event that could have a financial impact on the project of $450,000. This risk event has a 70 percent chance of occurring in the project. The project identifies a solution that will reduce the probability of the risk event to ten percent, but it will cost $260,000 to implement. Management agrees with the solution and asks that you include the risk response in the project plan. What risk response is this?

Where can Mark determine the priority of a risk given its probability and impact?

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?