A contingency plan should address:

A contingency plan should address:

PrepAway - Latest Free Exam Questions & Answers

A.
Potential risks.

B.
Residual risks.

C.
Identified risks.

D.
All answers are correct.

Explanation:
Contingency plans are developed as a result of a risk being identified. Contingency plans are pre-defined
actions plans that can be implemented if identified risks actually occur. One type of identified risk is a residual
risk. Residual risks are those risks that are expected to remain after implementing the planned risk response,
as well as those that have been deliberately accepted.
A contingency plan should address the risks found during risk assessment. Risk assessment includes both the
identification of potential risk and the evaluation of the potential impact of the risk.
Incorrect Answers:
A: Contingency plans should not just address potential risks. It should address identified risks and residual risks
as well.
B: Contingency plans should not just address residual risks. It should address identified risks and potential risks
as well.
C: Contingency plans should not just address identified risks. It should address potential risks and residual risks
as well.