Who is ultimately responsible for providing requirement specifications to the software-development t

Who is ultimately responsible for providing requirement specifications to the software-development
team?

A.
The project sponsor

B.
The project members

C.
The project leader

D.
The project steering committee

Explanation:
The project sponsor is ultimately responsible for providing requirement
specifications to the software-development team.