Which of the following is an implementation risk within the process of decision support systems?

A.
Management control

B.
Semistructured dimensions

C.
inability to specify purpose and usage patterns

D.
Changes in decision processes

Explanation:
The inability to specify purpose and usage patterns is a risk that developers need to anticipate while
implementing a decision support system (DSS). Choices A, B and D are not risks, but
characteristics of a DSS.