When performing a business impact analysis (BIA), which of the following should calculate the recovery time an

When performing a business impact analysis (BIA), which of the following should calculate the recovery time and cost estimates?

PrepAway - Latest Free Exam Questions & Answers

A.
Business continuity coordinator

B.
Information security manager

C.
Business process owners

D.
Industry averages benchmarks

Explanation:
Business process owners are in the best position to understand the true impact on the business that a system outage would create. The business continuity coordinator, industry averages and even information security will not be able to provide that level of detailed knowledge.