ISACA Exam Questions

What is the name of the process that this board is completing in your organization?

All projects that are presented in your organization must go through a board to review the return
on investment, risk, and worthiness of a project. All projects are considered but not all projects are
initiated. What is the name of the process that this board is completing in your organization?

A.
Project selection committee

B.
Change governance

C.
Project portfolio management

D.
Project portfolio management board

Explanation: