The use of a GANTT chart can:

The use of a GANTT chart can:

A.
aid in scheduling project tasks.

B.
determine project checkpoints.

C.
ensure documentation standards.

D.
direct the post-implementation review.

Explanation:

A GANTT chart is used in project control. It may aid in the identification of needed checkpoints but
its primary use is in scheduling. It will not ensure the completion of documentation nor will it
provide direction for the post-implementation review.