The activation of an enterprise’s business continuity plan should be based on predetermined cr

The activation of an enterprise’s business continuity plan should be based on predetermined
criteria that address the:

A.
duration of the outage.

B.
type of outage.

C.
probability of the outage.

D.
cause of the outage.

Explanation:

The initiation of a business continuity plan (action) should primarily be based on the maximum
period for which a business function can be disrupted before the disruption threatens the
achievement of organizational objectives.