What term is assigned to the low-level of stakeholder tolerance in this project?

You are the project manager of the NKJ Project for your company. The project’s success or failure
will have a significant impact on your organization’s profitability for the coming year. Management
has asked you to identify the risk events and communicate the event’s probability and impact as
early as possible in the project. Management wants to avoid risk events and needs to analyze the
cost-benefits of each risk event in this project. What term is assigned to the low-level of
stakeholder tolerance in this project?

What will be your reply?

You work as a project manager for BlueWell Inc. You are involved with the project team on the
different risk issues in your project. You are using the applications of IRGC model to facilitate the
understanding and managing the rising of the overall risks that have impacts on the economy and
society. One of your team members wants to know that what the need to use the IRGC is. What
will be your reply?