Exam CRISC: Certified in Risk and Information Systems Control

What will be your NEXT step?

You are working as the project manager of the ABS project. The project is for establishing a
computer network in a school premises. During the project execution, the school management
asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely.
You have discussed the change request with other stakeholders. What will be your NEXT step?

what term?

You work as a project manager for BlueWell Inc. Your project is using a new material to construct
a large warehouse in your city. This new material is cheaper than traditional building materials, but
it takes some time to learn how to use the material properly. You have communicated to the
project stakeholders that you will be able to save costs by using the new material, but you will
need a few extra weeks to complete training to use the materials. This risk response of learning
how to use the new materials can also be known as what term?