What technique will you use with this simulation?

CORRECT TEXT
You are the project manager of the AMD project for your organization. In this project, you are
currently performing quantitative risk analysis. The tool and technique you are using is simulation
where the project model is computed many times with the input values chosen at random for each
iteration. The goal is to create a probability distribution from the iterations for the project schedule.
What technique will you use with this simulation?

Which of the following risk processes is repeated after the plan risk responses to determine if the overall pr

You are the project manager of the NNN project for your company. You and the project team are
working together to plan the risk responses for the project. You feel that the team has successfully
completed the risk response planning and now you must initiate what risk process it is. Which of
the following risk processes is repeated after the plan risk responses to determine if the overall
project risk has been satisfactorily decreased?

Where will you record the mitigation response?

You are the project manager for your company and a new change request has been approved for
your project. This change request, however, has introduced several new risks to the project. You
have communicated these risk events and the project stakeholders understand the possible
effects these risks could have on your project. You elect to create a mitigation response for the
identified risk events. Where will you record the mitigation response?