ISACA Exam Questions

With the objective of mitigating the risk and impact of a major business interruption, a disaster re

With the objective of mitigating the risk and impact of a major business interruption, a disaster recovery plan should endeavor to reduce the length of recovery time necessary, as well as costs associated with recovery. Although DRP results in an increase of pre-and post-incident operational costs, the extra costs are more than offset by reduced recovery and business impact costs. True or false?

A. True

B. False

Explanation:

With the objective of mitigating the risk and impact of a major business interruption, a disaster- recovery plan should endeavor to reduce the length of recovery time necessary and the costs associated with recovery. Although DRP results in an increase of pre-and post-incident operational costs, the extra costs are more than offset by reduced recovery and business impact costs.