ISACA Exam Questions

Who is ultimately responsible for providing requirement specifications to the software- development

Who is ultimately responsible for providing requirement specifications to the software- development team?

A. The project sponsor

B. The project members

C. The project leader

D. The project steering committee

Explanation:

The project sponsor is ultimately responsible for providing requirement specifications to the software-development team.