Who assumes ownership of a systems-development project and the resulting system?

Who assumes ownership of a systems-development project and the resulting system?

A. User management

B. Project steering committee

C. IT management

D. Systems developers

Explanation:

User management assumes ownership of a systems-development project and the resulting system.