Which of the following tasks should be performed FIRST when preparing a disaster recovery plan?

Which of the following tasks should be performed FIRST when preparing a disaster recovery plan?

A. Develop a recovery strategy.

B. Perform a business impact analysis.

C. Map software systems, hardware and network components.

D. Appoint recovery teams with defined personnel, roles and hierarchy.

Explanation:

The first step in any disaster recovery plan is to perform a business impact analysis. All other tasks come afterwards.