Which of the following tasks should be performed FIRST when preparing a disaster recovery plan?
A. Develop a recovery strategy.
B. Perform a business impact analysis.
C. Map software systems, hardware and network components.
D. Appoint recovery teams with defined personnel, roles and hierarchy.
Explanation:
The first step in any disaster recovery plan is to perform a business impact analysis. All other tasks come afterwards.