Which of the following risks could result from inadequate software baselining?

Which of the following risks could result from inadequate software baselining?

A. Scope creep

B. Sign-off delays

C. Software integrity violations

D. inadequate controls

Explanation:

A software baseline is the cut-off point in the design and development of a system beyond which additional requirements or modifications to the design do not or cannot occur without undergoing formal strict procedures for approval based on a business cost-benefit analysis. Failure to adequately manage the requirements of a system through baselining can result in a number of risks. Foremost among these risks is scope creep, the process through which requirements change during development. Choices, C and D may not always result, but choice A is inevitable.