Which of the following is an appropriate test method to apply to a business continuity plan (BCP)?

Which of the following is an appropriate test method to apply to a business continuity plan (BCP)?

A. Pilot

B. Paper

C. Unit

D. System

Explanation:

A paper test is appropriate for testing a BCP. it is a walkthrough of the entire plan, or part of the plan, involving major players in the plans execution, who reason out what may happen in a particular disaster. Choices A, C and D are not appropriate for a BCP.