PrepAway - Latest Free Exam Questions & Answers

When should application controls be considered within the system-development process?

When should application controls be considered within the system-development process?

A. After application unit testing

B. After application module testing

C. After applications systems testing

D. As early as possible, even in the development of the projects functional specifications

Explanation:

Application controls should be considered as early as possible in the system- development process, even in the development of the projects functional specifications.


Leave a Reply