PrepAway - Latest Free Exam Questions & Answers

If an IS auditor observes that individual modules of a system perform correctly in development project tests,

If an IS auditor observes that individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further:

A. Documentation development

B. Comprehensive integration testing

C. Full unit testing

D. Full regression testing

Explanation:

If an IS auditor observes individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further comprehensive integration testing.


Leave a Reply