ISACA Exam Questions

Change control for business application systems being developed using prototyping could be complicat

Change control for business application systems being developed using prototyping could be complicated by the:

A. iterative nature of prototyping.

B. rapid pace of modifications in requirements and design.

C. emphasis on reports and screens.

D. lack of integrated tools.

Explanation:

Changes in requirements and design happen so quickly that they are seldom documented or approved. Choices A, C and D are characteristics of prototyping, but they do not have an adverse effect on change control.