which of the following risk prioritization options would this case be categorized?

You are the project manager of RFT project. You have identified a risk that the enterprise’s IT
system and application landscape is so complex that, within a few years, extending capacity will
become difficult and maintaining software will become very expensive. To overcome this risk the
response adopted is re-architecture of the existing system and purchase of new integrated
system. In which of the following risk

prioritization options would this case be categorized?

which of the following risk management capability maturity levels does your enterprise exists?

You are the risk official of your enterprise. Your enterprise takes important decisions without

considering risk credential information and is also unaware of external requirements for risk
management and integration with enterprise risk management. In which of the following risk
management capability maturity levels does your enterprise exists?