A risk assessment should be conducted:

A risk assessment should be conducted:

PrepAway - Latest Free Exam Questions & Answers

A.
once a year for each business process andsubprocess.

B.
every three-to-six months for critical business processes.

C.
by external parties to maintain objectivity.

D.
annually or whenever there is a significant change.

Explanation:
Risks are constantly changing. Choice D offers the best alternative because it takes into consideration a reasonable time frame and allows flexibility to address significant change.

Conducting a risk assessment once a year is insufficient if important changes take place. Conducting a risk assessment every three-to-six months for critical processes may not be necessary, or it may not address important changes in a timely manner. It is not necessary for assessments to be performed by external parties.