Who should be informed of this additional risk?

When interviewing the customer’s technical stakeholders, a governmental regulatory
compliance risk is identified. Who should be informed of this additional risk?

A.
IBM Sales Team

B.
IBM Project Manager

C.
stakeholder’s first line manager

D.
no one has to be informed as the risk is not important if it comes from the customer’s
technical stakeholders