Which statement about the ISD input stage is NOT TRUE?

Which statement about the ISD input stage is NOT TRUE?

PrepAway - Latest Free Exam Questions & Answers

A.
A job must have zero or one ISD input stages

B.
A job with an ISD input stage must have an ISD output stage

C.
Buffer size and timeout values can be supplied as job parameters

D.
Text over JMS binding is only available if you are using Network Deployment

Explanation:
https://www-
01.ibm.com/support/knowledgecenter/SSZJPZ_11.3.0/com.ibm.swg.im.iis.infoservdir.user.doc/topi
cs/t_isd_user_configuring_wisd_input_stage.html