Which statement about restartable sequence jobs is TRUE?

Which statement about restartable sequence jobs is TRUE?

A.
If a restartable sequence aborts, it can be restarted from Director.

B.
Choosing “Reset job” from Director will start the job where it left off.

C.
Checkpoints are always added to every eligible Job Activity stage in the sequence.

D.
There is no way to force a Job Activity stage to return if the sequence got beyond it.

Explanation:
http://www-01.ibm.com/support/docview.wss?uid=swg1JR46534