The company breaks up its engineering reviews in the following ways:?

An engineering company has requested a process to handle its engineering reviews. The
company breaks up its engineering reviews in the following ways: Complex engineering
efforts are handled by the Senior Engineers participant group (PG) Moderate engineering
efforts are handled by the Associate Engineers PG ?Simple engineering efforts are handled
by the Apprentice Engineers PG – All other engineering efforts are handled by the All
Engineers PG Review the business process diagram (BPD) below and the specified
behavior of the Engineers Swimlane. The Review Engineering Effort activity’s assignment is
based on a routing policy. The routing policy is dictated by the value of the BPD’s local
variable engineeringEffort. Which one of the following routing conditions for the Review
Engineering Effort activity will satisfy the company’s request?

Select the business process diagram that matches the description of the company’s process.

A design company has a process with 4 activities. The activity that occurs first is Submit
Design and it is implemented as a Human Service. The next two activities, Review Design
Engineering and Review Design Colors, occur in parallel, are always executed, and are
both implemented as a Subprocess. The final activity Approve Design, is implemented as a
Human Service and occurs after Review Design Engineering and Review Design Colors
have both been completed. Select the business process diagram that matches the
description of the company’s process.

which of the following approaches are valid to fix the problem?

A BPM application developer is asked by a system administrator to fix an issue with a failed
process instance in a on-line runtime environment. The system administrator has
determined that the problem is with a variable called tw.local.carSelection. The value of

tw.local.carSelection is incorrect and needs to be set to “Truck”. Assuming the BPM
application developer has been granted all security privileges required, which of the
following approaches are valid to fix the problem? (Choose two)

What statement will the BPM application developer make regarding the process of building an Ajax service in th

A BPM application developer has been called into a training session with a group of
developers who are new to IBM Business Process Manager V8.0. The BPM application
developer needs to describe the process of building an Ajax service to help the new

developers complete their assignment. What statement will the BPM application developer
make regarding the process of building an Ajax service in the training session? Creating an
Ajax service is:

what does the BPM application developer need to do?

A company wants to improve the time it takes to select a vendor for an order. They have
indicated that: each vendor works independently from one another. if any vendor provides a
price quote of less than $30, the process should move forward and close all open vendor
tasks. Review the following business process diagram (BPD) and the Output Mapping for
the Multi Instance Loop activity Obtain Order Quotes. The BPD’s local object quotes is of
type list of VendorQuote, which contains a property priceQuote of type Decimal. To meet
the company’s requirements, what does the BPM application developer need to do?
Change the Obtain Order Quotes activity to use:Change the Obtain Order Quotes activity to
use:


Page 3 of 612345...Last »