Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
A. The Project Manager.
B. The Development Team.
C. The Scrum Team.
D. The Product Owner.
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
A. The Project Manager.
B. The Development Team.
C. The Scrum Team.
D. The Product Owner.