Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

A. The Project Manager.

B. The Development Team.

C. The Scrum Team.
D. The Product Owner.