Why may a Business Change Manager be included within a project board structure of one of the program

Why may a Business Change Manager be included within a project board structure of one of the
programme’s projects?

A.
Monitor the project’s finances against the costs of the programme

B.
Provide a specific focus on transition and operational stability

C.
Provide the procedures to manage project risks

D.
Supply the project team with an understanding of the complete programme

Explanation: