EXIN Exam Questions

Which process or function is responsible for this activity?

One of the activities required for effective planning, coordination and evaluation of requested
changes is assessing the impact and required resources.
Which process or function is responsible for this activity?

A.
Change Management

B.
Configuration Management

C.
Release Management

D.
Service Desk