Which of the following Availability Management activities are considered to be proactive as opposed

Which of the following Availability Management activities are considered to be proactive as
opposed to reactive?
1) Risk assessment
2) Testing of resilience mechanisms

A.
None of the above

B.
Both of the above

C.
1 only

D.
2 only