EXIN Exam Questions

Which is one of the three levels of plan in PRINCE2?

Which is one of the three levels of plan in PRINCE2?

A.
Benefits Review Plan
Project Assurance is the responsibility of the corporate organization; quality assurance is the
responsibility of the Project Board

B.
Programme Plan
Project Assurance is independent of the Project; quality assurance is only independent of the
Project Manager

C.
Team Plan
Project Assurance may be delegated within a project; quality assurance must be undertaken by
the Project Board

D.
Project Brief
Project Assurance ensures compliance to standards within the project environment; quality
assurance ensures compliance across the organization

A.
Benefits Review Plan
Project Assurance is the responsibility of the corporate organization; quality assurance is the
responsibility of the Project Board

B.
Programme Plan
Project Assurance is independent of the Project; quality assurance is only independent of the
Project Manager

C.
Team Plan
Project Assurance may be delegated within a project; quality assurance must be undertaken by
the Project Board

D.
Project Brief
Project Assurance ensures compliance to standards within the project environment; quality
assurance ensures compliance across the organization

Explanation:
QUESTIONNO:160
Which of the following statements about quality assurance and Project Assurance is true?