Which is a valid statement about the Project Support role?

Which is a valid statement about the Project Support role?

A.
Can be performed by the Project Manager

B.
Is an optional role for a PRINCE2 project

C.
Produces Checkpoint Reports for the Project Manager

D.
Can be combined with the Project Assurance role