What product records any time tolerances agreed between the Project Manager and Team Manager?

What product records any time tolerances agreed between the Project Manager and Team
Manager?

A.
Product Description

B.
Work Package

C.
Project Initiation Documentation

D.
Stage Plan

Explanation: