What may be recorded in the risk register during the ‘identify – risks’ step?

What may be recorded in the risk register during the ‘identify – risks’ step?

A.
The probability and impact of an identified risk

B.
An action required to mitigate an identified risk

C.
A risk description expressed as a cause, event and effect

D.
The risk actionee for an identified risk response

Explanation: