Which step needs to be taken?

While implementing a new Symmetrix solution, the customer requests that five new hosts be
added to the project. This is outside the scope of the project.
Which step needs to be taken?

A.
Ask the account executive to modify the statement of work.

B.
Implement the new hosts as requested by the customer

C.
Notify the project manager to create a change request

D.
Notify the solution architect to redesign the solution