EMC Exam Questions

Which step needs to be taken?

While implementing a new Symmetrix solution, the customer requests that five new hosts be added to the
project. This is outside the scope of the project.
Which step needs to be taken?

A.
Ask the account executive to modify the statementof work.

B.
Implement the new hosts as requested by the customer

C.
Notify the project manager to create a change request

D.
Notify the solution architect to redesign the solution