EMC Exam Questions

Which action needs to be taken if the Backend Cabling Verification fails after a Data Center relocat

Which action needs to be taken if the Backend Cabling Verification fails after a Data Center
relocation?

A.
Contact PSE Lab for assistance.

B.
Relocate the cables shown as faulted.

C.
Replace the cables shown as faulted.

D.
Power down and re-start the Backend Cabling Verification script.